Day One, Sunday 18th
November 2012
After a five
hour drive/ferry/drive to Faridpur, with Opel (WA Research Manager) and Suman (WA Engineer) we
see the site.
As
it was at the last visit July 2012:
Site photo 18/11/12:
View from SW corner of site |
The
blockwork is nearly complete for all 6 tanks, which is tremendous progress
given the bad weather in the past fortnight.
There is a caretakers hut/ storage hut, tubewell installed and two
latrines-to-be.
View from SE corner of site, filter-base tank in foreground |
Filter base under construction |
Flat base tank under construction |
Getting the levels right using a tube of water |
Tomorrow, plastering starts...